Townsville Infrastructure Charges Register
A register of 59 infrastructure projects in Townsville linked to infrastructure charges on development approvals made from 1 July 2014. Each row gives the network (water, wastewater, transport and others), delivery mode, local government infrastructure plan references, project description, stage and dollar amounts for gross cost, funding, net position and actual spend to date.
Endpoints
Townsville Infrastructure Charges Register: search
/v1/records/townsville-infrastructure-charges-register/search10¢ per callServed by /v1/records/{slug}/search, which documents every parameter, the response shape and errors, and has a live playground.
| Query parameter | Description |
|---|---|
q | Words to find (prefix match, all must appear) in: network, delivery mode, capital plan identifier, project description. |
where | Exact-match filter `field:value`, repeatable, on: `network`, `delivery_mode`, `developer_s_permit_no_if_applicable`. |
fields | Comma-separated field slugs (below). Omit for all. |
limit | Records per page, 1 to 50 (default 25). |
offset | Items to skip, for the next page (`next_offset`). |
curl -X GET 'https://api.microburbs.com.au/v1/records/townsville-infrastructure-charges-register/search?q=Water' \
-H 'Authorization: Bearer test'test is the public sandbox key: it works only for the sandbox's allowlisted suburbs and addresses. Use your own key for anything else.
Townsville Infrastructure Charges Register: one record
/v1/records/townsville-infrastructure-charges-register/{record_key}5¢ per callServed by /v1/records/{slug}/{record_key}, which documents every parameter, the response shape and errors, and has a live playground.
| Query parameter | Description |
|---|---|
record_key | The record's record id. |
fields | Comma-separated field slugs (below). Omit for all. |
curl -X GET 'https://api.microburbs.com.au/v1/records/townsville-infrastructure-charges-register/1' \
-H 'Authorization: Bearer test'test is the public sandbox key: it works only for the sandbox's allowlisted suburbs and addresses. Use your own key for anything else.
About this dataset
Townsville local government area, Queensland. Approvals from 1 July 2014, with no end date. 59 rows. LGIP years in the data run up to 2031. Current to 2022-08-14; refreshed Yearly, as the register is republished..
What it is
This dataset is a register of trunk infrastructure projects in Townsville that are tied to infrastructure charges. It covers approvals from 1 July 2014 onward. Each row is one project or plan item, with its capital plan identifier and local government infrastructure plan (LGIP) references.
What it shows
It shows which networks the projects belong to, whether the city or a developer delivers them, and what stage each project has reached. It also shows gross cost, funding, net position and actual spend to date in dollars, plus the approximate size of each project in LGIP units such as metres or megalitres.
Why use it
Analysts can use it to see where trunk infrastructure is planned or being built, and how much of the cost is funded. It helps with assessing development feasibility, infrastructure charge exposure and the pipeline of water, wastewater and transport works in a growth area.
How it is built
We take the register as published and combine its two parts, one for manually calculated charges and one for charges processed through planning software, into one table of rows. Column headings are standardised and each row is given a record key. Values are kept as published, and blank cells stay blank.
Shortcomings
- Developer permit number and condition number are blank for 92% of rows, and the IA number is blank for 81%, so developer-delivered items cannot be reliably linked to approvals.
- Rows describe projects, not individual approvals or charge payments, so you cannot work out the charge on a given development from this data.
- Several columns have placeholder or zero values, such as LGIP year 0 and LGIP units 0. Treat them as unknown, not real values.
- Net values can be negative and large, and the gross, funding and net columns are not always consistent with each other. Check the totals before using them in calculations.
Fields
| Field | Unit | Description |
|---|---|---|
record_idRecord ID | Our key for the row, used to fetch a single record. | |
noItem number | count | Sequence number of the item as listed in the register, from 1 to 19; blank for some rows. |
networkNetwork | Infrastructure network the project belongs to, such as Transport, Wastewater or Water. | |
delivery_modeDelivery mode | Who delivers the project, such as the city (TCC) or a developer. | |
developer_s_permit_no_if_applicableDeveloper's permit number | Permit number for developer-delivered works, where one applies; mostly blank. | |
developer_s_condition_no_if_applicableDeveloper's condition number | Approval condition number for developer-delivered works, where one applies; mostly blank. | |
ia_no_if_applicableInfrastructure agreement number | Infrastructure agreement (IA) number, where one applies; blank for 81% of rows. | |
capital_plan_identifierCapital plan identifier | Code identifying the project in the capital plan, for example WAT136-1 or WWA71-1. | |
lgip_map_localityLGIP map (locality) | Map or locality number from the local government infrastructure plan; some values are 0. | |
lgip_idLGIP ID | One or more LGIP project identifiers, separated by commas where several apply. | |
lgip_yearLGIP year | year | Year the project is scheduled for in the LGIP, up to 2031; 0 where not set. |
lgip_unitsLGIP units | Unit of measure used for the project size in the LGIP, such as m or ML. | |
approx_size_unitsApproximate size | Approximate project size, expressed in the unit given in LGIP units. | |
project_brief_descriptionProject description | Short text description of the project, which may be truncated. | |
grossGross cost | AUD | Gross project cost in dollars. |
fundingFunding | AUD | Funding amount in dollars attributed to the project. |
netNet | AUD | Net dollar position for the project; can be negative. |
actuals_to_dateActuals to date | AUD | Actual spend recorded against the project so far, in dollars. |
stageStage | Project stage, such as Planning / Initiation, Design / Development, Construction / Implementation or Finalisation / Defects. |
Data source: Townsville City Council